News Center

Our company has been working tirelessly to expand its scale and industrial layout. We are confident that in the near future, the company will surely repay society with excellent results.

Public Notice Soliciting Opinions on the Completion Acceptance of Environmental Protection for the Hebei Dejin Glass Co., Ltd. 3# 800t/d Single Furnace Double-Line High-Quality Float Glass Sheet Production Line Project for Electronics and Automobiles


Release time:

2023-08-23

【资讯概要】

Hebei Dejin Glass Co., Ltd.3#800t/dHigh-quality float glass sheets for electronics and automobiles, one furnace, two lines

Production Line ProjectPublic Opinion Solicitation Announcement for Completion Acceptance of Environmental Protection

 

1、Brief Description of the Construction Project

(1)Construction LocationWithin the factory area of Hebei Dejin Glass Co., Ltd. in Shahe City, Xingtai City. Project center coordinates: East longitude114°35'22.37"、North latitude36°53'54.81"

(2)Construction content and scale:Project covers an area of120000square meters, with an annual output of high-quality float glass sheets for electronics and automobiles of480ten thousand weight boxes. The project does not increase production capacity or land use. The project will dismantle the existing800t/dfloat glass production line (3#production line), and reconstruct a one-furnace, two-line (800t/d300t/d+500t/d) production line of high-quality float glass sheets for electronics and automobiles with a daily melting capacity ofsquare meters. Purchase and installation of batching and weighing systems, cold-end equipment, etc. Project raw materials: silica sand, soda ash, dolomite, feldspar, limestone, cullet, etc.; production process: raw material80000melting-melting-tin bath-annealing-cold end-cutting-finished product warehousing; products: high-quality float glass sheets for electronics and automobiles.

2Construction of environmental protection facilitiesanddebugging effect

Waste gas:The waste gas from the glass melting furnace of the reconstruction project adopts“high-temperature section of waste heat boiler+SCRdenitrification+low-temperature section of waste heat boiler+sodium-based dry desulfurization and dust removal integrated process” for treatment, and then discharged through80ma high-level exhaust stack; particulate matter generated by the feeding system, batching system, and cullet system is treated by a film-covered filter bag dust collector, and then discharged through a high-level exhaust stack no less than15mhigh.In addition,this project strengthens the maintenance of production and environmental protection equipment,strengthens management,reduces the amount of unorganized waste gas emissions,after taking measures,it will not affect the surrounding atmospheric environment.

Wastewater:The ion exchange resin system cleaning wastewater, power plant circulating water system sewage, and waste heat boiler sewage of the reconstruction project are all used for dust suppression in the factory area. Part of the wastewater from the pure water preparation system is used for dust suppression in the factory area, and part is used for washing the workshop floor. Domestic sewage is treated by a septic tank and then enters the factory wastewater treatment plant together with the workshop floor washing wastewater. After treatment, it meets the standards of the “Wastewater Comprehensive Discharge Standard” (GB8978-1996) Table4secondary standard,“Urban Sewage Reuse Urban miscellaneous water quality”(GB/T18920-2020)"Road sweepingstandardand the inflow water quality requirements of Shahe City Xinhuan Wastewater Treatment Plant, part of which is used for dust suppression in the factory area, and part is discharged into Shahe City Xinhuan Wastewater Treatment Plant for deep treatment.

Noise: The main noise of the project is equipment noise.Low-noise equipment,foundation shock absorption,workshop sound insulationdistance attenuationwill not have a significant impact on the surrounding acoustic environment.

Solid waste:After the project is implemented,all solid waste generated will be properly disposed of or comprehensively utilized,and will not have a significant impact on the surrounding environment.

The project's waste gas, wastewater, noise,and solid waste will not have a significant impact on the surrounding environment,complying with the requirements of the environmental impact assessment and environmental impact assessment approval opinions,and the impact on the surrounding environment is relatively small.

3、Acceptance monitoring

Hebei Dejin Glass Co., Ltd.3#800t/dA production line project for high-quality float glass sheets for electronics and automobiles, with two production lines in one factoryEffective pollution control measures were adopted during design, construction, and operation. Environmental management was diligently implemented during construction and operation, effectively meeting the environmental protection requirements of the environmental impact report and its approval opinions. The environmental protection effect is good, and environmental protection has been well implemented."Simultaneous implementation of the three systemsSystem.

According to the acceptance monitoring results,wastewater,noise all meet the standards for discharge, solid waste is properly disposed of, and pollutant emissions meet the total amount control requirements. Based on this, our company believes that the project construction meets the acceptance conditions for completion of environmental protection.

4Scope and main matters of public participation:

The scope of public participation mainly covers the public in the project's impact area. The main matters for soliciting public opinions are as follows:

1)Public understanding of this project

2)Public concerns and requirements regarding the environmental protection of this project

3)Public opinions and suggestions on the environmental protection of this project

4)Public attitude towards the construction of this project

5Methods for public opinion submission

The public can submit their opinions through various methods, such as filling out questionnaires, telephone, fax, or email.Completion of environmental protection acceptance report for this projectThe brief version and public participation questionnaire can be obtained directly from the project constructor.

This publicannouncement period is from2023year8month23dayto2023year8month25day

    

Construction Unit:Hebei Dejin Glass Co., Ltd.         

Contact Person:Wang Gong           ContactPhone Number:15933394133                 

Mailing Address:Within the factory area of Hebei Dejin Glass Co., Ltd., Shahe City, Xingtai City.

Tag: